Cost of Change

Cost of change against project stage (after ICE 1996)

With profit margins becoming increasingly tight in the construction industry, developers are keen to manage and control risk and uncertainty, whether this be related to the cost and availability of materials, ground contamination, or archaeology. As a site’s archaeological potential is usually unknown, it is a case of moving the site from the unknown, to the known. It will usually be a staged process that is necessary, with each stage of work reducing the level of uncertainty, and therefore the level of risk. The earlier it is considered in a development program the better, as it allows more time to work out projected costs and incorporate any necessary changes to reduce these costs, into a design programme.

Example of Historic Environment Record data

Example of Historic Environment Record data

For many projects, most commonly the first step is a desk-based assessment, a non-intrusive survey of known evidence using a range of sources such as historic maps, aerial photos, and the Historic Environment Record, the local authority’s database of sites and findspots. This will determine the likely archaeological potential for a site and is a relatively rapid and cost effective technique. This may not be necessary for small projects however – such as extensions, or one or two dwellings, but developers can seek advice from the local authority archaeologist on this at an early stage.

Deposit model prepared to consider likely depths of archaeological deposits

Deposit model prepared to consider likely depths of archaeological deposits

More and more often however, as a result of NPPF, planners are asking for much more site specific information concerning the likely impact of a development. In these instances the document required is variously called a heritage statement or heritage impact assessment, where a consideration has to be made of the precise nature and extent of the likely impacts of the development upon the identified archaeological resource, as well as putting forward proposals as to how to mitigate the effects of the development upon this archaeology. This relates to both the physical impacts on the below ground archaeology as well as on the setting of monuments in the wider landscape. The issue of setting is a much wider topic, particularly with relevance to wind turbines, which are visible for many miles.

Gathering such information at an early stage in the design programme, through minimal and often non intrusive archaeological intervention can save the time and costs of either redesigning a development plan to avoid the need for further archaeological works, or archaeological excavations further down the line causing added costs and delays. Another thing to consider is engaging an archaeologist to monitor any geotechnical works that are being undertaken, as this will give a good indication of the likely depths of archaeology, made ground or truncation across a site.

More often than not, a DBA may identify an archaeological potential for a site but cannot within certainty determine the precise nature of the archaeological resource that may be present, in which case, intrusive works may be necessary to further characterise the archaeology present within the site – usually, where ground conditions are appropriate, geophysics is a common starting point, followed by trial trenching. As well as providing information on the below ground archaeology, geophysics can help inform and also limit the extent and therefore cost of subsequent targeted trenching.

Evaluation trenching strategy based on geophysical survey results

Evaluation trenching strategy based on geophysical survey results

This level of work should provide a planning authority with sufficient information upon the archaeological resource to allow for the determination of a planning application, and to establish appropriate measures, known as final mitigation, undertaken as a condition of planning. It may be the case that the trial trenching finds little or nothing of interest and that no archaeological condition is imposed. However, where this is not the case, developers will need to consider measures to either preserve the archaeological remains in situ, or to preserve by record, ie. dig it all up.

The concept of preserving the remains in the ground wherever possible, ie preservation in situ, is one of the prime considerations for archaeology and is considered preferable to excavation, ie preservation by record, as this is in itself a physically destructive process. Obviously it also reduces the developer’s bill for archaeology, and in purely financial terms, there is a consideration on such sites as to whether it would be cheaper to use a potentially more costly foundation design (eg piling) that preserves the archaeology, or fund an excavation that records the archaeology to the satisfaction of the planning authority, but allows a more cost effective foundation design to be used. Redesign of the development layout should also be considered, for example, relocating areas of public open space to protect areas of archaeological interest.

So there are ways to manage the archaeological risk, and the thing that we always try to stress to developers is to build in time to consider the likely archaeological issues that may affect a site. Most county councils employ archaeological officers whose role it is to advise planning officers and developers upon the likely implications of a development, and most archaeological contracting companies will also be happy to advise a client. It is sometimes possible to come up with ways to avoid or greatly reduce the need for archaeological investigations, and it is usually possible to manage the risks associated with the possibility of unforeseen costs or delays caused by unexpected findings. Archaeology is inherently unpredictable however, and we never know for certain what we are going to find. I am afraid that we as archaeologists can’t be held responsible for what the Romans did 2,000 years ago!

The initial stages of archaeological work can often be complex and differs greatly between sites depending on the individual peculiarities of the project. Often the first stage of work falls to the Heritage Research Department at AAL, consisting of Josh, Catriona and Jesse, and the writing of Desk-Based Assessments (DBAs).

Aerial photograph showing cropmakrs comprising circular enclosures

Aerial photograph showing cropmakrs comprising circular enclosures

A DBA attempts to assess whether there is likely to be any archaeological remains on or near a planned development, and whether the development will affect the setting or significance of known (and usually designated) heritage assets, such as listed buildings. The DBA is in essence a short research project exploring all the aspects of the history and archaeology of a particular piece of land. These can be buildings due for renovation or demolition, planned housing schemes, solar farms, cable lines and a whole variety of other reasons.

The starting point for a report is usually the local Historic Environment Record (HER); previously known as Sites and Monuments Records (SMRs). They are databases of information relating to the historic environment and contain information about archaeological works, buildings, landscapes, finds and a whole range of other things associated with the human past. You can access a lot of the information from Heritage Gateway if you are undertaking personal research.

The results of a HER search will tell us what known archaeological and heritage assets are located within defined area. However, this record is not everything. A report can also include sifting through the local archives for historical documents; indicating land use of the site over time, or investigating cropmarks shown on aerial photographs, and analysing maps of the past for evidence of shrunken villages. Some sites require a closer understanding of the underlying geology to predict whether prehistoric activity is likely, and others need to check whether 20th century buildings are likely to have truncated the archaeological resource.

Ridge and Furrow spotted on a site visit

Ridge and Furrow spotted on a site visit

Yet, part of the job also involves getting out the office and into the field (as we are still archaeologists!). Our site visits might include visiting ancient monuments, exploring parks and gardens, inspecting and recording old buildings, and visually assessing seemingly innocuous land, searching for potential clues of archaeological remains that might lie beneath. Without visiting the site it can be impossible to know how it relates to the landscape surrounding it.

A DBA is often undertaken at the pre-planning stage in order to highlight the potential for archaeological remains in advance of construction taking place. This allows the developer to prevent damage to the archaeological resource and the associated costs of excavation by changing the specifics of the development. For instance, the developer might choose to leave open spaces for recreation on houses estates over areas of known archaeological interest in order to avoid disturbing underlying remains. You never know, your local park might be on the ground of a Roman villa or a medieval castle! In addition, DBAs allow the local planning authorities to make decisions about whether or not excavation is required for planning permission, in cases where it is not practical to change the nature of the development. That’s when archaeologists get their hands dirty!

Preparing DBAs can be really rewarding projects for people who want to expand their knowledge of British Archaeology. You have to know a little bit about everything, and know where to start looking for more information and when to spend more time exploring something.